Joint Measurement for the Month of July 2008


Joint Measurent will carry out before end of every Month. PMC need to verified the quantity of work or material before the claim can submit to the Client. Joint measurement will involved 3 party... (1) PMC(project Management Consultant (2) Consultant (to advise on technical matter) (3) Contractor


Sheet pile ready to claim, its already deliver to the Contractor Store yard at Gurun kedah.


Rebar at store yard, Gurun Kedah.